Print   

Tuesday 01 December, 2009

African Eagle Resources PLC

Preliminary Results from Phase 2 Metallugical T...





                   UPDATE ON METALLUGICAL TESTS ON
          AFRICAN EAGLE'S DUTWA NICKEL PROJECT IN TANZANIA

   Preliminary Results from Phase 2 Metallugical Testwork Received

*                      Initial column test results show rapid leach
  kinetics
*                      Up to 70% nickel extraction after just 16 days
  acid leaching
*                      Low acid consumption of 200-230 kg/tonne
*                      Promising initial tank leach results


African  Eagle's  Managing  Director  Mark  Parker  comments,  "These
results  are  extremely  encouraging,  showing  very  fast   reaction
kinetics and  confirming  the good  nickel  extraction and  low  acid
consumption of the Dutwa ores.  The results show that the project  is
amenable to both  heap leach  and tank leach,  and point  the way  to
further tests to determine the  optimum process parameters. The  fast
leaching reaction, low  acid consumption and  good nickel  extraction
are extremely positive indicators for the viability and profitability
of the project."


African Eagle has received interim results from the current phase of
metallurgical testwork, which is being conducted by Mintek of South
Africa.  The results include the first tank leach and column leach
test data, together with further "bottle roll" leach test results and
rock property test results.

The test results will help  to determine the best extraction  process
and to optimise parameters such as acid concentration, residence time
and leach temperature in the  engineering design for the  feasibility
study.

Column tests

Three column tests are being conducted to investigate the likely
behaviour of the ore under heap leach conditions. Coarsely crushed
ore (25mm or less in size) is packed into vertical plastic pipes, 1
metre high and 200mm diameter, and continuously irrigated with
sulphuric acid.  The acid dissolves the nickel and other metals as it
percolates down the column.

After only 16 days, 60% to 70% of the nickel had been extracted, with
low net acid consumption of 200 to 230kg/t.  This shows extremely
fast leaching reaction kinetics, much faster than most published
nickel laterite data.  Although column test data cannot be simply
scaled up to determine full-sized heap behaviour, these results are
extremely encouraging.

Fast reaction kinetics has important profitability implications for
the heap leach method, as it means that working capital will not be
tied up for many months while the heap reaches full productivity.  At
Caldag in Turkey, for example, operator European Nickel plc reports
that almost one year of leaching was required to extract 60% of the
nickel from trial heaps and 540 days to extract 80%. Mintek reports
that other nickel laterite ores it has column-tested have also taken
much longer to achieve comparable recoveries.

Tank leach tests

Three tank leach tests have been conducted to investigate the ore
behaviour under high temperature agitated vat leach conditions.  The
ore samples were pulverised to three different particles sizes for
these tests. The tests were conducted over 24 hours, but again, very
fast reaction kinetics was seen and almost all of the nickel
extraction occurred within the first hour. The fast initial leaching
exhausted the acid quickly and nickel extractions reached 64%, but
future tests using higher initial acid concentrations should give
better recovery.

Bottle roll tests

Three additional bottle roll tests were conducted to investigate the
effects of changing the acid concentration and the solids to liquid
ratio.  The results showed that leaching efficiency falls if the acid
concentration is reduced.

Physical property tests

The results of the following tests have also been received:

*          Bond impact work index
*          Bond abrasion index
*          Bond ball work index
*          Bond rod work index
*          Uni-axial compressive strength
*          Agglomerate stability tests
*          Bulk and true SG determination
*          Moisture content
*          Natural and complete sizing

The physical property test  results will be  used in the  engineering
design for the feasibility study.



Technical terms
A  glossary  of  technical  terms  used  by  African  Eagle  in  this
announcement  and   other  published   material  may   be  found   at
www.africaneagle.co.uk/p/glossary.asp


For further information:

Mark Parker
Managing Director
African Eagle
+44 20 7248 6059
+44 77 5640 6899

Nicola Marrin
Seymour Pierce Limited, London
Nominated Adviser
+ 44 20 7107 8000

Charmane Russell
Russell & Associates, Johannesburg
+ 27 11 8803924
+27 82 8928052

Ed Portman / Leesa Peters
Conduit PR, London
+44 20 7429 6607
+44 77 3336 3501


About African Eagle

African Eagle is  a diversified mineral  exploration and  development
company operating  in  eastern  and  central  Africa.  The  Company's
principal advanced assets are the Dutwa nickel laterite discovery  in
Tanzania, where the Company completed  a scoping study in June  2009,
and its 49% interest in the Mkushi Copper Mines joint venture project
in Zambia, for which  a draft feasibility study  was completed in  Q4
2008.

African Eagle  is  evaluating  a  second  promising  nickel  laterite
deposit at Zanzui in  Tanzania and has defined  a JORC gold  resource
estimated at half  a million  ounces at  its Miyabi  gold project  in
Tanzania. The Company  holds a well-balanced  portfolio of  promising
earlier stage gold, copper, platinum and uranium projects,  including
the Ndola  and Mokambo  projects in  the Zambian  Copperbelt and  the
Igurubi gold project in Tanzania.

Zambia,  Tanzania  and  Mozambique,  the  sites  of  African  Eagle's
projects, are all  countries which have  highly prospective  geology,
relatively low  above-ground risks  and track  records of  successful
major investments in the metals and minerals industries.

In December  2008, African  Eagle resolved  to prioritise  the  Dutwa
project, because  the  Board  believes that,  of  all  the  Company's
projects, it offered the greatest potential to add value. To take its
other discoveries into production, African Eagle is seeking  industry
partners with records  of successful  mine development,  by means  of
joint ventures, farm-ins, spin-outs or other mechanisms.

About the Dutwa Project

African Eagle has discovered a significant nickel laterite deposit in
the Dutwa  project  area  in the  Lake  Victoria  Goldfield.   Within
Tanzania, the  project  is  favourably situated  100km  east  of  the
railhead at Mwanza and close to the main Mwanza-Nairobi trunk road, a
major power line and the shore of Lake Victoria.

The Company holds a 90% interest,  with option to acquire 100%,  over
the Dutwa laterite deposit and in 2009, signed a Letter of Intent for
an option and joint venture over another nickel laterite at  Ngasamo,
5km west. In  all, African Eagle  has explored a  total area of  more
than 750km� in the project area.

Since the discovery of the Dutwa nickel deposit in June 2008, African
Eagle has  explored the  project very  quickly and  cost-effectively,
including resource  drilling and  an independent  resource  estimate;
laboratory metallurgical and mineralogical tests which revealed  that
the  deposit  could  be  processed  efficiently  by  sulphuric   acid
leaching.  On 24 June 2009, the Company announced the results of  its
"proof of concept" scoping study. The study, by GRD Minproc of Perth,
Western Australia,  indicated that  the project  can be  economically
viable, and African  Eagle has  now begun work  towards a  definitive
feasibility study.

The Study indicates that Dutwa, if it were in production today, would
be profitable. Earnings, on an EBIT  basis, would be of the order  of
$110 million per annum  on average over the  life of mine, giving  an
internal rate of return around 20%.

As a potentially low-cost producer, the upside for the Dutwa  project
is considerable if nickel prices are above the $7/lb used in the base
case.  The following table shows  the key metrics for several  upside
cases.


Ni price          US$/lb  9.00  8.50  8.00  7.50  7.00  6.50
Life of mine EBIT   $M   2,600 2,300 2,000 1,800 1,500 1,200
Pre-tax IRR         %       31    27    24    21    17    13
Post-tax IRR        %       27    24    21    18    15    11
Pre-tax NPV         $M     640   530   420   310   200    90
Post-tax NPV        $M     430   350   270   190   110    30





Base case:                                 Abbreviations:

Nickel price = US$ 7/lb ($15,430/tonne)    EBIT = Earnings before
Cobalt price = US$ 10/lb                   interest and tax
Discount rate = 10%                        IRR = Internal Rate of
Transport cost = US$100/tonne              Return
(8�/tonne/km)                              NPV = Net Present Value
Tax rate = 30%, fiscal incentives not      DCF = Discounted cash flow
accounted                                  analysis
Royalty = 3%
                                           All numbers stated to 2
The financial modelling was conducted in   significant digits
US dollars with an estimated accuracy of
�30%




The Study adopted a fairly broad brush approach to many of the costs,
to demonstrate "proof of concept" and provide indicative  economics.
GRD Minproc estimated  individual capital  and operating  costs to  �
30%, based on  their considerable experience  with nickel  laterites.
These variables will be determined with more accuracy and  confidence
during the forthcoming feasibility work.

The Study identified  several key  areas where  further testwork  and
detailed study are especially likely to result in improvements to the
"bottom line"  or  to important  gains  in confidence.   These  areas
include:

*        Improved global deposit model and the potential for early
  "high-grading".  The Ngasamo resource will be drilled and
  incorporated into a more sophisticated global resource model and
  mining plan.  From this, it will be possible to establish whether
  richer ore can be mined first, giving increased early cash-flow and
  an improved NPV.
*        Ore beneficiation and project scale. The capital and
  operating costs of the plant would be reduced if mechanical
  beneficiation of the ore prior to leaching yields a smaller tonnage
  of richer material for processing through the plant.
*        Advanced leaching testwork. Column and vat leach tests at
  bench and pilot scale will determine the best operating conditions
  to optimise nickel extraction, including acid concentration,
  residence time and temperature.
*        Reagent cost reductions.  The cost of reagents, notably
  sulphur and lime, will be a significant component of operating
  costs and profitability will increase considerably if these costs
  are minimised.  Transport is a substantial part of the reagent
  costs and ways to minimise this will be investigated, as will the
  availability of more local sources, particularly of lime.
*        More sophisticated fiscal and economic modelling.  Tanzania
  offers a number of tax incentives for exploration and mine
  development, which were not fully accounted in the Study economic
  model.

In August,  the Company  raised £3.3M  additional capital  through  a
Placing and Offer, to address  these issues and progress the  project
towards feasibility.  Further metallurgical testing has commenced  on
drill core samples  at Mintek  laboratories in South  Africa and  the
Company has started infill drilling at Dutwa and resource drilling at
Ngasamo.

African Eagle acquired the Dutwa project for its gold potential,  but
the Company's  exploration team  quickly  recognised that  there  was
significant nickel laterite potential. There is very little  outcrop,
so the Company conducted extensive ground magnetic surveys to  reveal
the underlying  structure  and  geology. The  Company  also  compiled
historical  data,  including  detailed  geological  maps  and  trench
results dating from 1956,  when rock chip  samples from the  trenches
over the  ultramafic  rocks were  reported  as yielding  up  to  1.9%
nickel.

Greenstones and granites underlie the project area. The  greenstones,
of Archaean  Nyanzian  age,  are mostly  metamorphosed  volcanic  and
sedimentary rocks,  with  some banded  iron  formation in  the  east.
Several large ultramafic bodies occur within the greenstones and  the
nickel laterites form a blanket up to 60m thick on top of these.

To investigate  the nickel  discovery,  the Company  undertook  trial
drilling in  June  2008. The  results  were very  encouraging  and  a
139-hole reverse circulation (RC) drilling programme was completed to
delineate the  resource.  African  Eagle  also  undertook  a  10-hole
diamond drill  programme to  obtain  core samples  for  metallurgical
testing and density measurements.

In November 2008, African Eagle announced an initial Inferred Mineral
Resource estimate of 31  million tonnes at an  average grade of  1.1%
nickel and 0.034%  cobalt. At a  cut-off grade of  0.5% nickel,  this
gives Dutwa a  contained metal  endowment of some  340,000 tonnes  of
nickel and 11,000  tonnes of  cobalt.  The estimate  was prepared  by
independent consultants  SRK Consulting  (UK) Ltd  in line  with  the
Australasian Code for Reporting of Mineral Resources and Ore Reserves
(the JORC  Code).  A little  additional  drilling and  more  advanced
geostatistics and deposit  modelling will  be needed  to upgrade  the
resource to Indicated category.

Ngasamo Hill, 5km  west of  the Dutwa deposit,  is geologically  very
similar and holds a laterite deposit of the order of 15 to 20 million
tonnes, which would increase  the global resource  at Dutwa from  the
currently defined 31 million tonnes at  1.1% nickel, to some 45 -  50
million tonnes.  Drilling and metallurgical  tests will be needed  to
confirm the  size, grade  and compatibility  of Ngasamo.   Under  its
agreement with Ngasamo's owners, (Safina  a.s. of the Czech  Republic
and its Tanzanian subsidiary  Precious Metals Refinery Company  Ltd),
African Eagle can earn an interest of  at least 50% and up to 75%  in
Ngasamo by  carrying out  exploration and  evaluation work,  up to  a
feasibility study.

Mintek Laboratories in Johannesburg  investigated the mineralogy  and
metallurgy of mineralised drill  samples from the deposit,  including
extended 'bottle  roll' sulphuric  acid  leach tests  to  investigate
metal recoveries  and  acid  consumption.  Mintek  also  carried  out
mineralogical characterisation by  X-ray diffraction (XRD),  scanning
electron microscopy (SEM) and polished section work.

The bottle roll test results showed nickel extractions of 70-90% with
an average of 83%.  Cobalt extractions were mostly in the range 70 to
85%. The acid consumptions, averaging 209kg/t, are very low  compared
to other Ni laterite ores worldwide.

The mineralogical investigations show that the laterite is  extremely
silica-rich, with  low iron  and magnesium  content, indicating  that
Dutwa is not a typical laterite nickel deposit.  Mintek believes that
much of the nickel and cobalt occurs in "wad" with manganese  content
of 20-60%, nickel content of  up to 20% and  cobalt content of up  to
10%.

The unusual mineralogy  of the  deposit is highly  beneficial, as  it
results in lower acid consumption and  is expected to give good  heap
leach permeability  or  favourable liquid-solid  separation  in  tank
leaching. The concentration of nickel and cobalt in the manganese wad
offers  the  possibility  that  mechanical  selection  of  high-grade
material  may  allow  reduced  throughput  and  hence  a  lower  cost
processing plant.

The Company  is also  investigating other  potential nickel  laterite
deposits in  Tanzania, and  has  completed a  trial programme  of  RC
drilling to test a laterite at its Zanzui project, 60km to the  south
of Dutwa.   Results included  42m at  1.05% nickel  (including 6m  at
2.80%) and 33m at 0.91% nickel (including 9m at 1.41%).

---END OF MESSAGE---




This announcement was originally distributed by Hugin. The issuer is 
solely responsible for the content of this announcement.





Investegate takes no responsibility for the accuracy of the information within the site.


The announcements are supplied by the denoted source. Queries about the content of an announcement should be directed to the source. Investegate reserves the right to publish a filtered set of announcements. NAV, EMM/EPT, Rule 8 and FRN Variable Rate Fix announcements are filitered from this site.



Investegate      © 2012 FE. All rights reserved.