The Company is pleased to announce that its newly built carbon-in-leach ('CIL') plant ('Plant') at Raub is performing ahead of management's expectations, since its first gold pour in February, and had produced 4,140 troy ounces of gold to the end of May. Plant performance is expected to improve further as we ramp up production towards anticipated levels via both an increase in tonnage throughput and further optimisation of the CIL process.
Following start up, the performance of the Plant and mining operations have also been monitored with respect to their impact on the environment and operational safety. All relevant measurements and reports are within the levels set by the relevant authorities and the Company will remain vigilant in its approach to environmental and safety factors.
Dato' Sri Andrew Kam commented, 'We are pleased to be able to report that the Plant is progressing steadily up to its planned levels of throughput and production. I look forward to updating the market on our production progress and other plans over the coming months.'
Further information :
Dato' Sri Andrew TY Kam
Chairman & Chief Executive
Peninsular Gold Limited
Tel : +60 12 331 0828
Patrick Watson
Finance Director
Peninsular Gold Limited
Tel : +44 7799 88 5653
David Nabarro / Richard Greenfield
Ambrian Partners Limited
Tel : + 44 207 634 4700
Jerry Keen
Astaire Securities plc
Tel: +44 207 448 4492
Ed Portman
Conduit PR Limited
Tel: +44 207 429 6607
This information is provided by RNS
The company news service from the London Stock Exchange
END
TSTGIGDLXBBGGCR