NLMK restarts blast furnace #4 


NLMK announces today that it has restarted blast furnace #4 after a complete overhaul. The blast furnace of a total capacity of 1.7 million tonnes per year was idled in November 2008


As part of the five-month overhaul of the 2000m3 unitrefractory was replaced, charging equipment and air heaters were renovated, the furnace shell was partially changed and cast houses repaired. The overhaul took place over five months at cost of RUR 180 million.


In February, NLMK also recommissioned blast furnace #3 with total capacity of 1.6 million tonnes per year, and blast furnace #2 with capacity of 770,000 tonnes per year. 


Currently, NLMK's main production site is running all five blast furnacesSteel production in Lipetsk in 2009 is expected to reach 8.3 million tonnes.  





This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCBBGDUUBGGGCI

Investegate takes no responsibility for the accuracy of the information within the site.


The announcements are supplied by the denoted source. Queries about the content of an announcement should be directed to the source. Investegate reserves the right to publish a filtered set of announcements. NAV, EMM/EPT, Rule 8 and FRN Variable Rate Fix announcements are filitered from this site.



Investegate      © 2012 FE. All rights reserved.