Gippsland Limited ('Gippsland' or the 'Company')


PROJECT & CORPORATE UPDATE

  • Project financing for Abu Dabbab on track

  • Abu Dabbab EPCM contract negotiations well advanced for completion by end October '08

  • highly prospective tenements in Eritrea anticipated to be granted October '08



ABU DABBAB PROJECT FINANCE

Directors of Gippsland Limited [ASX, AIM: GIP, Deutsche Börse: GIX] do not foresee that the recent international financial instability will adversely affect project financing for the Company's world-scale 44.5 million tonne Abu Dabbab tantalum-tin project. Negotiations are presently in progress with KfW Bankengruppe which is owned 80% by the German Federal Government and 20% by the German federal states (Bundesländer). The KfW legal due diligence associated with the Abu Dabbab project is nearing completion.

ABU DABBAB EPCM

Detailed negotiations with several engineering groups for the Abu Dabbab Engineering, Procurement, Construction Management (EPCM) contract have been undertaken during the past three months. An EPCM contract is expected to be executed between the Company and the successful engineering group prior to the end of October 2008.

USA INSITUTIONAL SHAREHOLDING

An evaluation of the Gippsland share registries in the United Kingdom and Australia was recently carried out to identify potential exposure to USA-based institutional shareholders, who may be more exposed to financial instability. To the best knowledge of the Directors, the Company has no USA-based institutional shareholders, save for the Washington based International Finance Corporation* which is part of the Standard and Poors AAA rated World Bank Group. Holding 25 million Gippsland shares (8.16%), the IFC is a substantial Gippsland shareholder. 

ABU DABBAB TANTALUM PRODUCT NOT RADIOACTIVE

Gippsland Directors see that recent industry participant announcements relating to tantalum feedstock price increases and possible shortages along with increasing tantalum end product prices, bodes well for the Abu Dabbab project which is predicted to set a new industry standard for low production costs whilst producing a premium grade product having a Ta2O5 content in excess of 40%. Importantly, the Abu Dabbab product will not be classified as an International Maritime Organisation (IMO) Class 7** radioactive material as the combined U3O8 and ThO2 will be well below the maximum limit of 0.1%.  Most sources of tantalum feedstock have difficulty in achieving this 0.1% limit.

The Directors are very confident that the Abu Dabbab project will play a crucial role in the supply of tantalum feedstock to the global industry for several decades.

ERITREAN COPPER-GOLD TENEMENT APPLICATIONS

The Company's 100% owned subsidiary Nubian Resources PLC ('Nubian Resources') has made application for three highly prospective Prospecting Licences in the northern part of Eritrea.  The Company would not normally announce the lodgement of tenement applications, however as the Eritrean Ministry of Energy and Mines has released details of the Nubian Resources applications in various internationally distributed publications, the Directors believe that disclosure of these tenement applications to the general market is warranted.


These licences each of 100km2 cover alteration targets identified from satellite interpretation and are prospective for base metal mineralisation similar to the world class Bisha volcanic massive sulphide (VMS) deposit located in south-western Eritrea. They are also similar in structure to the Sub-Sahara Resources NL Zara gold project located immediately to the south of the three Nubian Resources application areas.


The Company has been actively evaluating the regional mineral potential of the Arabian-Nubian Shield which is the host of Gippsland's 44.5 million tonne Abu Dabbab and 98 million tonne Nuweibi tantalum projects plus the Company's Wadi Allaqi gold copper-nickel prospects in Egypt.  


The Arabian-Nubian shield extends over large parts of EgyptSudanEthiopia and Eritrea, Saudi Arabia and Jordan. In Eritrea a number of large base metal and gold deposits have recently been discovered.  The Nevsun Resources Ltd Bisha base metal-gold deposit is due to commence production in 2009 and expected to produce around 1Moz of gold, 340kt of copper and 499kt of zinc over a ten year life. The Emba Derho project managed by Sunridge Gold Corporation near the capital Asmara is emerging as a 51 million tonne base metal-gold deposit containing 0.87Moz of gold, 453kt of copper and 1.043kt of zinc. Further north, to the immediate south of the Nubian Resources applications, the Sub-Sahara Resources NL Zara project contains slightly in excess of 1Moz of gold at a grade of 6.31g/t.


The Nubian Resources applications are in the same structural corridor as the 1Moz Zara project and a similar volcanic setting as that hosting the Bisha deposit.  The Directors anticipate that the tenements will be granted during October 2008.


RJ (Jack) Telford

Executive Chairman 

Gippsland Limited

www.gippslandltd.com  


For further information please contact:


Jack Telford


Gippsland Limited


T: +61 8 9340 6000


E: jtelford@gippslandltd.com  




Richard Hail

John Gilbert

Fox-Davies Capital Ltd

Fox-Davies Capital Ltd

T: +44 20 7936 5200

T: +44 20 7936 5200

E: richard.hail@fdcap.com 

E: john.gilbert@fdcap.com 



Nandita Sahgal

Matthew Thomas

Seymour Pierce Limited

Seymour Pierce Limited

T: +44 20 7107 8000

T: +44 20 7107 8000

E: nanditasahgal@seymourpierce.com 

E: matthewthomas@seymourpierce.com 



Jane Stacey

Fiona Hyland

Investor Relations

Investor Relations

M: +44 792 292 3306

M: +44 777 600 5847 

E: jane@conduitpr.com 

E: fiona@conduitpr.com


 IFC fosters sustainable economic growth in developing countries by financing private sector investment, mobilising capital in the international financial markets, and providing advisory services to businesses and governments. IFC helps companies and financial institutions in emerging markets create jobs, generate tax revenues, improve corporate governance and environmental performance, and contribute to their local communities. The goal is to improve lives, especially for the people who most need the benefits of growth.  www.ifc.org/about 


**  The shipment of IMO Class 7 radioactive materials is highly restricted by international shipping regulations to the extent that they are not permitted to enter the European Economic Zone, Japan and numerous other countries unless shipped by a dedicated vessel. The road transportation of IMO Class 7 materials within Europe and numerous other jurisdictions is extremely difficult to the point of being impractical.



This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCBKLFFVKBFBBK

Investegate takes no responsibility for the accuracy of the information within the site.


The announcements are supplied by the denoted source. Queries about the content of an announcement should be directed to the source. Investegate reserves the right to publish a filtered set of announcements. NAV, EMM/EPT, Rule 8 and FRN Variable Rate Fix announcements are filitered from this site.



Investegate      © 2012 FE. All rights reserved.